Chrysal Website 2027 · Extended draft · 19 October 2026
RFP 15 · 18 · 19
From a shared direction to a strong launch.
An indicative 2027 roadmap with concrete milestones, decision points and Chrysal’s involvement. The final schedule will follow budget approval and discovery.
Selected scenario
Core launch
Including stabilization
Approximately 24 weeks
Start · planning example
11 January 2027
The phases below follow the roadmap from the proposal: kick-off on 11 January 2027, launch in weeks 21–22 (late May or early June, after the Mother’s Day peak) and monitoring through week 24. The final dates follow budget approval and discovery. Future options will receive a separate roadmap and will not automatically shift the base launch.
01
Before the start
November – December 2026
Selection & budget decision
Commission and availability confirmed
Partner selection, clarification, scope selection and budget approval.
Chrysal’s contribution
Sponsor, Marketing, IT and procurement assess the proposal and assumptions.
Dependency
Internal investment approved
02
Week 1–2
January
Discovery
Go/no-go 1 · Direction and scope approved
Site structure and navigation, six customer journeys, content model, CMS and localisation agreements and the SEO baseline.
Chrysal’s contribution
Stakeholders join one or two discovery sessions; access to sources, analytics and exports.
Dependency
Sources, accounts and experts available
03
Week 3–6
Late January – February
Design
Go/no-go 2 · Design approved
Five key page designs and a recognisable block library.
Chrysal’s contribution
Brand and content review; consolidated feedback within five working days.
Dependency
Visual material and brand agreements available
04
Week 6–13
February – early April
Development
Platform ready on the test environment
A working WordPress platform with blocks, content types, languages and markets, search, forms and the technical SEO/GEO foundation.
Chrysal’s contribution
Short weekly check-in; technical information and local contact data.
Dependency
Design and content model approved
05
Week 11–18
March – May
Fill workshop & content
Content deadline week 18
Fill workshop in week 11; Chrysal fills content and translations, with redirect mapping in parallel.
Chrysal’s contribution
Product owner, experts and local marketeers supply and review content; content deadline week 18.
Dependency
Usable export, rights and translation capacity
06
Week 19–20
May
User acceptance test
Go/no-go 3 · Launch approved
Customer journeys and editorial tasks tested with real content; findings resolved and rechecked.
Chrysal’s contribution
Product owner and editors test; the privacy officer reviews consent.
Dependency
Content complete, no open blocking findings
07
Week 21–22
Late May – early June
Launch
Production accepted
Controlled go-live after the Mother’s Day peak, with verified forms, measurements and a recovery route.
Chrysal’s contribution
Product owner, IT and contact follow-up available on the agreed working day.
Dependency
Chrysal gives content and technical launch approval
08
Week 22–24
June
Monitoring & stabilisation
Short evaluation and handover
Two weeks of monitoring, issues fixed directly and a short evaluation.
Chrysal’s contribution
Consolidate reports; discuss results and follow-up priorities.
Dependency
Reliable production and measurement data
Governance that monitors progress
One product owner
Chrysal consolidates feedback and content-related decisions. The sponsor decides on scope and budget; experts validate claims and local teams validate translations.
Fixed working cadence
Weekly progress updates on schedule, budget and risks; fortnightly demonstrations during the build. Feedback within five working days is a working assumption.
No hidden scope growth
The impact of every change on time, money and management is assessed in advance. Decisions are recorded, with written approval before additional work.